Cut
3240 mm
flat blank

Live statistics

Cutting length

3240 mm

Hooks added

288 mm

Bends cut

48 mm

Unit system
Hooks
Straight length(m) Help
m

Bent shape length along centreline.

Bar diameter(mm) Help
mm

Bar diameter.

Bends (90 deg)(nos) Help
nos

Count of 90 deg bends at 2d each.

Results update live as you type

How you compare — standard sections

SectionDepth (mm)Mass (kg/m)A (cm²)Iₓ (×10⁶ mm⁴)Sₓ (×10³ mm³)
UB 305×165×40 · Steel I-beam 30440.351.385560
UB 457×191×67 · Steel I-beam 45467.185.52941290
UC 254×254×73 · Steel column 25473.193.1114895
RC 300×500 (C30) · Concrete beam 5003751500312512500
Glulam 140×450 · Timber beam 4502963010634725
SHS 200×200×8 · Hollow section 20047.460.436.9369

Indicative values for scheme design only. Always verify against the manufacturer / code tables (AISC Steel Manual, SCI Blue Book, ACI detailing) before ordering steel or pouring concrete.

Plans & details

Detail

Rebar detail sketch

Bar marks, bends, hooks and laps per IS 456 and ACI 318. Extend bars past supports plus development length.

Path

Placing layout

Spacing, cover and curtailment plan. Verify clear gaps for vibration and concrete flow.

Check

Site verification

Confirm bar diameters, counts and cover blocks against the BBS before pouring.

Typical details for scheme design. Replace placeholders with project drawings (1200×630 JPG or SVG line work in /public/plans/civil/). Do not scale from web images — use figured dimensions.

Design verification checklist

Work through before issuing results — 1/6 verified (17%).

Results

Optimal

Flat cutting length

3240mm

Straight plus hooks minus 90 deg deductions.

Hook addition

288mm

Hook tails added.

Bend deduction

48mm

2d per 90 deg bend subtracted.

Visualizations

Results Overview

3,240mmFlat cutting length
288mmHook addition
48mmBend deduction

Formula

Flat blank equals the bent centreline shape plus hook tails, shortened for stretch at each bend.

Lcut = Lstraight + hooks - bends

Alternative Form

hooks: 2x9d or 2x12d | bends: n x 2d at 90 deg

Variables

SymbolNameUnitDescription
LcutCutting lengthmmFlat blank.
hooksHook tailsmmAdded length.
bendsDeductionmmSubtracted stretch.

Explanation

Add tails, subtract stretch.

Derivation

Length conservation of the bar axis: blank plus stretch equals finished shape with tails.

Step-by-Step Calculation

Follow each step to understand how the result is calculated from your inputs.

Step 1

Enter straight length, diameter, bends and hooks

Result: Bar fixed
Step 2

Read hook and bend parts

Result: Allowances issued
Step 3

Read flat cutting length

Result: Blank issued
Final Answer
3240

Worked Examples

See how the calculator works with different scenarios.

Scenario

Stirrup-adjacent tie bar.

Inputs

straight:3
d:12
nBends:2

Calculation

Hooks 288 mm, bends 48 mm. Cut 3000+288-48 = 3240 mm.

Result

Cut = 3240 mm

Interpretation

Cut one trial bar and check cover.

Understanding Your Result

Your Result: Flat cutting length = 3240 mm · Hook addition = 288 mm · Bend deduction = 48 mm

Typical range: 12 mm bars with hooks cut about 240 mm over straight.

What This Means

Flat millimetres to cut so the bent bar lands on size.

Why It Matters

Wrong blanks waste steel and break cover.

Professional Interpretation

Issue cutting length with the hook and bend breakup per mark.

Recommendations

  • •Verify one bar mark by hand per schedule
  • •Keep cover and spacing buildable for vibration
  • •Add wastage and laps before ordering steel

Learn — structural behaviour, deeply

Shape in, blank out.

1 · The two equations that run every site

ΣF_y = 0

Vertical balance

Upward reactions must equal total downward load. Missing 1 kN here means a 1 kN shear error everywhere downstream.

ΣM = 0

Moment balance

Moments about ANY point must cancel. Take moments about one support to eliminate it and solve the other directly.

ΣF_x = 0

Horizontal balance

Zero for vertical-only loading — but the pin still needs checking once wind, soil or inclined loads appear.

Worked derivation (simply supported, point load): ΣMleft = 0 ⇒ Rb·L − P·a = 0 ⇒ Rb = P·a/L, then ΣFy = 0 ⇒ Ra = P − Rb = P·(L−a)/L. UDL adds w·L/2 per side acting at midspan. That is the entire calculation — everything else is bookkeeping.

2 · Support types — what each one can (and cannot) do

SupportReactionsAllowsWatch out
Roller1 (vertical)Horizontal slide + rotationProvides NO lateral restraint — pair with a pin or bracing.
Pin / hinge2 (vertical + horizontal)Rotation onlyMoment released here — detail the hinge, never weld it rigid by accident.
Fixed / clamped3 (+ moment)Nothing (fully restrained)Attracts large moments; settlement or temperature causes locked-in stress.
Propped cantilever3 (indeterminate ×1)Rotation at propNeeds compatibility (deflection = 0 at prop) — equilibrium alone is not enough.
Continuous (3+ supports)4+ (indeterminate)Rotation over interior piersSolve by superposition / moment distribution / software; reactions shift with stiffness.

3 · Factor-impact table — what moves your reactions most

FactorTypical impactWhy
Load position (a/L)Linear, dominantMoving P toward a support shifts ~100% of P onto it. Ra = P·(L−a)/L — position matters more than span.
UDL intensity (w)∝ w·L totalEach extra 1 kN/m on a 6 m beam adds 3 kN per reaction. Self-weight alone is often 1–5 kN/m on concrete.
Span length (L)∝ L for UDLDoubling L doubles UDL reactions and quadruples UDL moment (wL²/8). Keep spans tight where possible.
Overhang length (c)∝ c/L upliftUplift at the far support = P·c/L. A 2 m overhang with 10 kN on a 5 m span pulls down 4 kN — needs hold-down.
Fixity (pinned → fixed)Redistributes ~10–30%Fixed ends attract moment and shed midspan moment. Never assume fixity you have not detailed.
Support settlement (Δ)0 (det.) / large (indet.)Determinate beams just rotate; continuous/fixed beams develop locked-in moments ≈ 3EIΔ/L².
Dynamic / impact+10–100%Static reactions must be amplified for cranes, machinery, footfall (see ASCE 7 Ch. 4, AISC DG11).
Load combination× 1.2–1.6 (LRFD)1.2D + 1.6L + 0.5(Lr/S/R) governs most beams. Reactions for strength ≠ reactions for service checks.

4 · Code provisions you must cite on drawings

  • ASCE 7 load combinations (LRFD): 1.4D · 1.2D + 1.6L + 0.5(Lr/S/R) · 1.2D + 1.0W + 1.0L … Strength reactions use factored loads; bearing/deflection checks use service (unfactored) loads.
  • ACI 318 (concrete): strength-reduction ϕ = 0.65–0.90; development/lap lengths Ch. 25; one-way shear + punching Ch. 22. Reactions feed directly into Vu ≤ ϕVn.
  • AISC 360 (steel): Ch. F/G/H for moment/shear/combined; bearing at supports per J7–J8; bracing per App. 6. Connection must develop the computed reaction — a beam is only as strong as its seat.
  • Eurocode basis (EN 1990): ULS 1.35G + 1.5Q; SLS G + Q (characteristic). National annexes adjust factors — confirm the project annex.
  • Serviceability (all codes): live-load deflection ≈ L/360 floors, L/240 roofs; total ≈ L/240. Vibration: AISC DG11 / SCI P354 for rhythmic or office floors.

5 · Pro workflow (5 minutes per beam)

  1. Sketch the free-body diagram: every load incl. self-weight, every support, dimensions.
  2. Solve ΣM then ΣF — write both lines on the calc sheet so a checker can follow.
  3. Verify: re-take moments about the OTHER support; residual must be ≈ 0.
  4. Draw shear then moment (reactions are the SFD starting values).
  5. Size the support: bearing stress, padstone, bolt/weld group, foundation pressure.
  6. File: keep the input → reaction → SFD/BMD → support chain on one page.

6 · Field traps (where reactions go wrong)

  • • Forgetting self-weight: a 300×600 concrete beam weighs 4.5 kN/m — on 6 m that is 13.5 kN per support.
  • • Assuming fixity: a “fixed” sketch with two bolts is a pin. Model what you detail.
  • • Ignoring uplift: overhang + wind can reverse a bearing — light roofs lift off.
  • • Mixing factored/service: never compare a factored reaction against an allowable soil pressure.
  • • Point load at the wrong station: 0.5 m error on a 10 kN load swings reactions by P·Δa/L.

7 · The 3-check rule (sign-off standard)

  1. Math check: ΣFy and ΣM both close to zero with project units printed.
  2. Sanity check: reactions sum to total load; heavier side sits under heavier load; UDL symmetry gives Ra ≈ Rb.
  3. Load-path check: every reaction lands on something sized for it — beam → seat → column → footing → soil, no floating numbers.

Practical Tips

  • •Split dead vs live early — factoring depends on it
  • •Include self-weight; concrete often dominates
  • •Report service values to 1 decimal for bearings and footings

Common Mistakes

Service load checked against factored capacity
Keep a service column (settlement, soil, deflection) and a factored column (strength) side by side.
Self-weight omitted
Add member weight into the total first.
Wrong units in one term
Convert everything to the page unit system before combining terms.

Assumptions

This calculator makes the following assumptions to provide estimates:

Static gravity loading: No impact, vibration or seismic amplification unless the page applies one.
Nominal material properties: Code-grade materials per project data; confirm lightweight or high-strength cases.
Scheme-level accuracy: Closed-form code clauses for preliminary and check calculations.

Limitations

Be aware of these limitations when using this calculator:

Verify supports and pattern: Pattern loading, continuity and support settlement need their own runs.
Confirm local code values: Loads, factors and minimums vary by jurisdiction.

Frequently Asked Questions

Answers to common questions about this calculator.

Which hook option?
Match the detail: 9d for 90 deg cogs, 12d for seismic hooks.
What if angles differ?
Use the bend page for mixed angles, then feed totals here.
Trial bar needed?
Yes, prove cover on one bend before batch cutting.
Is this final?
No, scheme value only.
How do I find reactions for a simply supported beam?
Take moments about the left support: Rb = (P·a + w·L·L/2) / L, then Ra = P + w·L − Rb. Always re-check by taking moments about the right support — the residual must be ≈ 0.
What does a negative (downward) reaction mean?
The support must pull DOWN instead of pushing up — net uplift from overhangs, pattern loading or wind. Provide a hold-down strap, anchor or ballast; a gravity-only bearing will lift off.
Do I include the beam self-weight?
Yes, always. A 300×600 mm concrete beam weighs ~4.5 kN/m — on a 6 m span that adds ~13.5 kN per support. Bundle it into the UDL before solving.
Service vs factored loads — which do I report?
Report BOTH in separate columns: service (unfactored D+L) for deflection, bearing, settlement and soil checks; factored LRFD (1.2D + 1.6L) for member strength. Never compare a factored reaction with an allowable soil pressure.
What is the difference between a UDL and a UVL?
A UDL (uniformly distributed load) is constant intensity over a length (kN/m). A UVL (uniformly varying / triangular) runs zero-to-max — e.g. soil or hydrostatic pressure. They integrate differently, so use the matching calculator.
How do I turn a floor area load into a beam line load?
Multiply the area load (kN/m²) by the tributary width (m) draining to the beam: line load = area load × tributary width. Add the beam self-weight, partitions and finishes first.
What is tributary area?
The floor/roof area whose load flows to one member — bounded by halfway lines to adjacent members. Tributary area × area load = the point/line load that member must carry.
Which load combination usually governs a beam?
For strength: 1.2D + 1.6L (+ 0.5 for roof live/snow/rain) per ASCE 7 LRFD. Service D+L governs deflection and bearings; 0.9D + 1.0W governs uplift and overturning.
LRFD vs ASD — does it change the reactions?
No — equilibrium is the same. The design PHILOSOPHY differs: LRFD factors loads up (1.2D+1.6L) against factored resistance (ϕRn); ASD keeps service loads against allowable stresses (Rn/Ω). Keep the two systems in separate columns.
Pin, roller or fixed — how do I choose the support model?
Model what you DETAIL. Masonry/steel seats and two-bolt end plates are pins (moment released); moment frames, welded rigid joints and well-anchored cantilevers earn fixity. When in doubt, the pinned assumption is conservative for midspan moment but NOT for uplift.
What deflection limits apply to beams?
Typical code limits: live-load deflection L/360 for floors (L/240 roofs), total-load L/240, cantilevers 2L/360-ish per IBC Table 1604.3. Always check under SERVICE loads with the correct (cracked, long-term) stiffness.
How do I convert kN ↔ kips and m ↔ ft?
1 kN = 0.2248 kips (1 kip = 4.448 kN); 1 m = 3.2808 ft. Moments: 1 kN·m = 0.7376 kip·ft. Every calculator on this site has an SI/Imperial toggle that converts all displayed values.
Shear vs bending moment — which sizes what?
Shear sizes stirrups/webs and connections (V ≤ ϕVn); bending moment sizes flexural steel and the section (M ≤ ϕMn via section modulus S: stress = M/S). Deflection is governed by stiffness EI, a third independent check.
Where does the maximum moment occur?
Where shear crosses zero: under a midspan point load, or at x = R/w under UDL (span moment = R·x − w·x²/2). On continuous beams also check the hogging peaks OVER interior supports — they often govern.
What is section modulus and how do I use it?
S = I/c (mm³): the geometric bending efficiency of a section. Bending stress = M/S; required S = factored moment / allowable (or design) stress. Compare against the standard-section table on each page.
How do I quickly check a steel beam?
Three checks per AISC 360: bending (Ch. F incl. lateral-torsional buckling over the unbraced length), shear (Ch. G), and deflection (L/360). Then verify the connection develops the end reaction.
How do I quickly check a concrete beam?
Flexure per ACI 318: ϕMn = ϕ·As·fy·(d − a/2) with ϕ = 0.9 (tension-controlled); one-way shear Vc + Vs (Ch. 22); deflection via minimum thickness or direct computation with cracked stiffness and long-term multiplier.
What is development length and why does it matter?
The embedment needed for a bar to reach yield (ld, ACI 318 Ch. 25). A perfectly computed moment capacity is worthless if the bar pulls out — extend bars past inflection points and hook or develop them at supports.

Related Calculators

Explore more calculators related to this topic.

Glossary

Technical terms used in mortgage calculations explained in plain language.

Reaction
Force (or moment) a support exerts on a member to maintain static equilibrium (ΣF = 0, ΣM = 0).
Simply supported
Beam on one pin + one roller. Resists vertical load; allows rotation and (at roller) horizontal movement.
Fixed support
Clamped end resisting force AND moment; prevents rotation. Used in cantilevers and fixed frames.
UDL / UVL
Uniformly distributed load (constant kN/m) vs. uniformly varying load (triangular, zero-to-max).
Tributary area
Floor/roof area whose load drains to one member. Line load = area load × tributary width.
Factored load
Service load × LRFD load factor (e.g. 1.2D + 1.6L) for strength design per ASCE 7.
Serviceability
Deflection, cracking and vibration limits under day-to-day (unfactored) loads.
Uplift
Net downward-hold requirement: a negative (downward-pulling) reaction, common on overhangs.

Authoritative References

Trusted sources and standards referenced by this calculator.

Applicable Standards

ACI 318 — Building Code Requirements for Structural ConcreteAISC 360 — Specification for Structural Steel BuildingsASCE 7 — Minimum Design Loads and Associated CriteriaEurocode 2 (EN 1992) — Design of Concrete StructuresEurocode 3 (EN 1993) — Design of Steel StructuresIBC — International Building Code (structural chapters 16–23)